Henry, Illinois | Illinois Route 18

Removal and replacement of the existing concrete deck; structural steel, substructure repairs, bearing replacement, cleaning and painting of structural steel; approach work, guardrail and electrical work.

Using the specialized overhead crane system, Halverson developed an innovative jacking and cribbing plan, and executed a thorough work plan, allowing the project to be completed 150 days ahead of schedule — earning Halverson the largest incentive payment ever made by IDOT.

Contract Value: $3,663,294
Completion Date: November 1988
Owner: Illinois Department of Transportation — District 3
Location: Henry, Illinois






Lacon, Illinois | Illinois Route 17

Removal and replacement of the existing concrete deck, structural steel below the deck; substructure repairs; bridge lighting; bearing replacement; cleaning & painting of structural steel; approach work and guardrail.

Halverson worked closely with the local Chamber of Commerce to keep the local merchants informed on the progress of the project. Using the overhead crane system, the project continued through periods of high water. This allowed Halverson to complete this project thirty days ahead of schedule. (A Joint Venture with Midwest Foundation Corp.)

Contract Value: $ 3,500,000
Completion Date: September 1990
Owner: Illinois Department of Transportation — District 3
Location: Lacon, Illinois






Marseilles Phase I & Phase II | FAS 268

Phase I: Construction of a nine span steel plate girder bridge, lighting, approach pavement. Halverson submitted forming and striping plans to coordinate clearance, and minimize impact to river traffic.

Phase II. Removal of existing steel truss bridge and erosion control. Coordination with Coast Guard & Lockmaster to shut down barge traffic during bridge removal.

Contract Value: $3,046,078 | $775,892
Completion Date: December 1997 | October 1998
Owner: Illinois Department of Transportation — District 3
Location: LaSalle County, Illinois






Peoria, Illinois | McCluggage Bridge

Rehabilitation of the Eastbound McCluggage Bridge over the Illinois River in Peoria & East Peoria, Illinois. Substructure repair, structural steel repair, roadway & navigational lighting, new concrete deck, painting and cleaning of structural steel, and joint repair.

Halverson planned weekly jobsite personnel partnering meetings, discussing schedule, upcoming work items, issues requiring immediate resolution. CPM scheduling programs used, for quick updating and electronic transmission among partnering participants. Overhead crane system used to facilitate deck removal and replacement. (A Joint Venture with Midwest Foundation Corp.)

Contract Value: $ 26,128,362
Completion Date: November 2000
Owner: Illinois Department of Transportation — District 4
Location: Peoria & Tazwell County, Illinois






Peru, Illinois | Illinois Route 251

Removal and replacement of the existing concrete deck, structural steel below the deck, concrete substructure repairs. Additional work included bearing repairs, cleaning & painting of structural steel and approach work.

Halverson used an innovative method to support the suspended truss section while the pin and links were reworked and replaced. This allowed the use of the overhead crane system to continue to run throughout the truss while this work was being done. These methods allowed the project to be completed 30 days ahead of schedule. (A Joint Venture with Midwest Foundation Corp.)

Contract Value: $ 6,754,988
Completion Date: November 1992
Owner: Illinois Department of Transportation — District 3
Location: Peru, Illinois






Spring Valley, Illinois | Illinois Route 89

Removal and replacement of the existing concrete deck; structural steel replacement; new bridge rails, bridge lighting, bearing replacement, cleaning and painting of structural steel; guardrail replacement and substructure repairs.

Using the overhead crane system, the project continued through flooding. This project was also completed thirty days ahead of schedule and thus earning a maximum incentive bonus. (A Joint Venture with Midwest Foundation Corp.)

Contract Value: $3,800,000
Completion Date: May 1990
Owner: Illinois Department of Transportation — District 3
Location: Spring Valley, Illinois